Challenge #2 (IHP SG13CMOS5L) is underway; the proposal field closed in August 2026 and schematic design is in progress, ahead of a November 9, 2026 tapeout. Challenge #3 (Wafer.Space GF180MCU) is currently accepting proposals, due August 31, 2026, ahead of a December 14, 2026 tapeout.

Challenge #2 detailed milestones: IHP SG13CMOS5L

DateMilestone
Jul 13, 2026Challenge launches
Jul 13–27, 2026Write proposals
Jul 27, 2026Proposals due (grace period through Aug 10, 2026)
Jul 27–Aug 31, 2026Schematic design & pre-layout verification
Week of Aug 31, 2026Schematic design review
Aug 31–Sep 28, 2026Layout & post-layout verification
Week of Sep 28, 2026Layout design review
Sep 28–Oct 19, 2026Chip top-level integration
Week of Oct 19, 2026Final design review
Nov 9, 2026IHP tapeout
Nov 16, 2026Test prep work begins
May 10, 2027Return from manufacture; packaging & assembly
Jun 28, 2027Parts shipped to designers; testing & characterization begins
Aug 30, 2027Test results due back

Post-tapeout milestones (packaging, shipping, and testing dates) will be added once set.