Challenge #2 (IHP SG13CMOS5L) is underway; the proposal field closed in August 2026 and schematic design is in progress, ahead of a November 9, 2026 tapeout. Challenge #3 (Wafer.Space GF180MCU) is currently accepting proposals, due August 31, 2026, ahead of a December 14, 2026 tapeout.

Challenge #3 detailed milestones: Wafer.Space GF180MCU

Challenge #3's Wafer.Space tapeout date is now set, so this schedule is fixed.

DateMilestone
Aug 17, 2026Challenge launches
Aug 17–31, 2026Write proposals
Aug 31, 2026Proposals due
Aug 31–Oct 5, 2026Schematic design & pre-layout verification
Week of Oct 5, 2026Schematic design review
Oct 5–Nov 2, 2026Layout & post-layout verification
Week of Nov 2, 2026Layout design review
Nov 2–Nov 23, 2026Chip top-level integration
Week of Nov 23, 2026Final design review
Dec 14, 2026Wafer.Space tapeout
Dec 21, 2026Test prep work begins
May 31, 2027Return from manufacture

Post-tapeout milestones (packaging, shipping, and testing dates) will be added once set.